Stock mould or new tooling

A stock mould already exists, so you pay for parts and not for the cavity. Colour becomes the main variable, and a colour change means a production run of its own — which is why a custom colour usually has a higher minimum than a standard one.

New tooling is justified when the shape is your differentiator, and it is quoted as a separate line with an ownership term. Ask who owns the mould and what happens to it if you move suppliers; the answer belongs in the contract, not in an email.

What a sample should prove

A sample is not a colour card. It should prove three things: that the closure seats and releases the way the specification says, that the wall thickness holds when the pack is squeezed or dropped, and that the decoration lands where the artwork says it will.

Ask for a first-off sample from the production mould, not a lab sample. A part made on a lab press proves the design; a part made on the production tool proves the order.

Payment terms, plainly

The common structure is a deposit against the order and the balance against documents or before shipment. A letter of credit moves the risk to the banks but adds cost and paperwork, which is usually not worth it below a certain order value.

Whatever the split, tie each payment to an event you can verify: deposit to production start, balance to a passed inspection or to a bill of lading. A payment tied to a date rather than an event is a payment you cannot control.

Inspection and Incoterms

Agree the inspection basis before production, not after. AQL sampling with a stated level and a stated defect classification is a specification; "we check everything" is not.

Incoterms decide where your risk ends, and the three that come up most are FOB, CIF and DDP. FOB puts the risk on you once the goods are on board; CIF carries it to the destination port but not to your door; DDP is the only one where the supplier handles duty and delivery. Choose by how much of the logistics you want to own, not by which number is lowest.